Stop Summer Shocks

FIGURE 1 - Methods of haul rope grounding

The one system of a lift that can almost be counted on to give problems when lift start-up time arrives next winter is the electrical, safety, and communication system. Frequently, trouble occurs before the winter season arrives. A mid-summer inspection may reveal a relay or entire electrical panel burned out although all power to the lift had been off and no evidence of a direct lightning strike is apparent. Even lifts operated throughout the summer will occasionally become “ill” overnight. Infrequently, a lift will suffer major damage due to a direct lightning strike. Precautions and protective measures can be taken which will reduce the possibility of trouble due to electrical storms.

Safety standards and good practice require that certain lift parts be grounded. The newly revised ANSI Standard (B77.1-1973) adds specific requirements not previously required. What must be grounded permanently? All structures (terminals, intermediate stations, line towers, the haul rope, and electrical circuits other than low voltage safety circuits). The newly revised B77. 1-1973 Standard requires that the haul rope be grounded at all terminals and stations. Previously, grounding of the haul rope at one location was adequate. Step one in your summer program is to provide for the additional grounding of the haul rope. A variety of methods are available to accomplish this. Figure 1 shows several methods in use. Consultation with the lift designer is recommended. Normally, the grounding of the haul rope provides a path of travel for electrical current from the haul rope to a terminal or station structure. Until this path is completed to the earth, little has been accomplished.

Advertisement

Pro Deals Billboard