Winter 1975 Issue

Danger– Load Test In Progress

Chief Cableways Engineer, USDA—Forest Service

Chalkboard sign reading "Danger — Load Test in Progress" standing above an aerial lift control panel.

Load testing of aerial lifts has been performed for many years and the procedures are fairly well established. Still accidents or “near misses” occur frequently when load-testing tramways and lifts. Such occurrences dramatize the potential danger of this most-essential operation, and the necessity for rigid adherence to basic requirements and proper procedures for testing. The accidents occur when established prerequisites and procedures are disregarded, when testing is done prematurely to accommodate scheduling, and when inexperienced or careless personnel either direct or participate in testing.

In the near future, lift designers, who are most familiar with the equipment and the facilities, may be required to submit for approval lift test procedures along with design drawings and specifications. Administrative authorities will establish prerequisites to testing as well as minimum test requirements. Typical of such requirements is the U.S. Forest Service Technical Report ETR-7300-2, “Guide to Post Construction Inspection and Load Testing of Aerial Passenger Tramways and Ski Lifts.” Some codes and safety orders establish minimum requirements as is the case of the current ANSI B77.1 Standard, Section 2.1.14.1.

Advertisement

Creative Design Card

Advertisement

Creative Design Billboard