The Voice of the Mountain Resort Industry  |  Est. 1962

Advertisement

Commerce B - Leaderboard

July 2008 Issue

Tower of Power

Jiminy Peak's wind turbine has been up and running for a full season now. Was the payoff worth it?

The 1.5-megawatt wind turbine at Massachusetts’ Jiminy Peak Mountain Resort began generating electricity last August. But another natural force—gravity—nearly ruined the carefully laid plans of Jiminy’s CEO and president, Brian Fairbank, to tap the readily available power of the wind.

By late June, after years of research, preparation, and perseverance, the turbine had arrived at the resort. A two-mile long access road had been spooned into ski runs to accommodate transport of the 250 tons of components.

First up was the 300-ton crane. The 29-foot-wide base scraped up against the rock sidewalls of the road, but made it. The 320-foot boom was disassembled for transport in 25 separate trips.

Next up was the bottom part of the 253-foot tower. At 41 tons, it was also the heaviest component yet. The truck was hitched to a D-9 bulldozer for the trip up the mountain. But more brute power was needed. A D-6 bulldozer was added to the D-9 to pull, and then a companion team, a D-6 and D-9, were added at the rear, to push. That did the trick.